At any rate, when we use the formula S = TL a TE for the calculation of slack time , we get the answers given in Table 5-5. A glance back at the network itself will reassure you that the critical path is indeed 1-2-4-6, but you cannot describe the critical path in this instance as having no ... A better definition then of the critical path with respect to its slack time is: the path with the least algebraic value of slack.